Greenwood Haq’s Villa at Mirpur DOHS

Location: Plot 1108, Road 9/A (new), 48 (old)

  • Project Start Date                       : November 2012

  • Project Completion Date          : March 2015

  • Land Size                                      : 04 Katha

night_002

Haqs Villa Night View

 

Greenwood Haq’s Villa

Greenwood Haq’s Villa

 

 

IMG_3400

Machine Made Bricks all through

2013-05-28 07.38.46

Curing from day 1

2013-05-28 07.32.57

1st Class Machine Made Brick used from early stage till finishing

2013-05-28 07.40.15

Early Stage Picture (1st Class Machine Made Brick and Shylet Sand used)

2013-02-24 11.47.26

Strong Foundation

2013-02-24 11.49.59

All through 1st Class Stone Chips used including column and slab

160220131086

BSRM 500 w XTREME TMT Bar from bottom to top

160220131087

BSRM Xtreme 500w TMT Bar starting from foundation till rooftop

2013-05-28 07.36.52

To ensure more strenght HALF lift casting from bottom to top

IMG_2112

Strong foundation

2013-02-13 09.08.13

Precision from Irreplaceable stage

09122012906

Full time close supervision from piling work, continues & smooth flow of work

IMG_2206

FOAM LUB used from Baral Chemical

IMG_2194

Foam Lub from Baral Chemical with TWENTY years warranty

2014-07-23 14.24.38

1st Class machine made brick with Perfect workmanship

230720142549

Professional skilled workmanship, skilled labour : smooth finishing

2014-07-23 14.25.07

1st Class Machine Made brick used from bottom to TOP, Classic brick

IMG_3596

August 2014 View

HV 21 Oct 2014 _2

Progress on 25 October 2014

GW Haqs Villa 15 January 2015

15 January 2015

 